Hindustan Construction Company has received two orders from Hindalco Industries to fabricate pot superstructure and complete civil and RCC structural work for pot line for Aditya Aluminium smelter project at Lapanga in Orissa aggregating to INR 2.99 billion.
The first order involves design, engineering, procurement and fabrication of pot superstructures, the value of the contract is INR 1 billion. The project is to be completed in 19 calendar months from the date of issue of this order. The second order involves complete civil and structural work involving site grading, civil and architectural work for pot line.
The value of the contract is INR 1.99 billion. The project is to be completed in 15 calendar months from the date of issue of this order.
(Sourced from IRIS)