Lack of Coal supply hurting power sector - Experts
273 times viewed.
Friday, 02 Dec 2011
EmailButton
Pdf_button

BS reported that even as Indian power sector is bleeding heavily with mounting losses of distribution companies and shrinking margins of power generation, industry players blame coal availability and lack of transmission infrastructure for acting as a spoilsport for the industry.

Industry insiders have raised an alarm over the worsening condition of fuel linkages, as not all the new power producers are likely to get domestic coal.

Mr Ravi Sharma CEO of Adani Power said that "For the coal based power producers, fuel has become the biggest game spoiler. Fuel availability is shrinking and power capacities are rising. In such a situation, Indian power industry can't survive on imported coal.”

Public sector mining major Coal India meets more than 80% of the requirement with coal production of about 431 million tonnes achieved last year.

However, company officials maintained that more than CIL, private mining players have to scale up their production so as to meet the growing coal requirements and reduce the dependence on the mining major.

Mr HK Vaidya CGM sales and marketing of CIL said that "Of the country's total available coal resources of 276 billion tonnes, nearly 100 billion tonnes falls under 214 blocks that have been allotted to private players for mining. They have to ramp up their production. At CIL, we aim to achieve production target of about 452 million tonnes in the current year.”

According to data provided by Central Electricity Authority, India's power generation from coal fell by 4% during April 2010 and February 2011 to 503.9 billion units (a unit= 1 kilowatt hour) from the target.

Meanwhile, Gujarat has stood tall with its power policy and surplus power capacities even in the current troubled times of power industry. Saurabh Patel, minister of state for energy and industries, Government of Gujarat informed that a strong political will and policy backing has helped Gujarat to stand tall in tough times.

Mr Patel said that "The times are not good for Indian power sector. Domestic coal availability is limited and imports are costly. Secondly, power generation from gas is also in bad shape due to slowing KG production. But Gujarat is saved from this and we could make profits.”

He further maintained that even as nearly 500 MW of gas fired capacities stand idle due to lack of fuel supply, the state could manage to offset the losses worth INR 480 crore per year. He said that "We could offset the losses from power trading on exchanges as we have excess power capacities," said Patel.

Mr Patel called for faster execution of evacuation infrastructure as despite having demand in southern corridor of the country power is not supplied due to lack of inter-state transmission lines.

(Sourced from BS)

Expanded Metal by Anping County Huijin Wire Mesh Co., Ltd.
Galvanized Steel by Beijing Xinruilufeng Industry and Trade Co., Ltd.
Wire Mesh Manufacturers & Suppliers
Aluminium Sheets Manufacturers & Suppliers

jspl
Stemcor
More Indian News
 
Disclaimer|Copyright Policy|Privacy Policy|About us|Feedback|Contact us|FAQ|Site Map|Know about SteelGuru