Macroeconomic indicator - ISM report on business for Sept 2012 - Buying Policy
183 times viewed.
Wednesday, 17 Oct 2012
EmailButton
Pdf_button

Average commitment lead time for Capital Expenditures decreased 1 day to 123 days. Average lead time for Production Materials decreased 1 day to 54 days. Average lead time for Maintenance, Repair and Operating Supplies remained unchanged at 27 days.

Percent Reporting

Capital ExpendituresHand to Mouth30 Days60 Days90 Days6 Months1 Year+Average Days
Sep '1225514182315123
Aug '1223713192315124
Jul '1229713182112109
Jun '1226109202015118



Production MaterialsHand to Mouth30 Days60 Days90 Days6 Months1 Year+Average Days
Sep '12183822164254
Aug '12163726154255
Jul '12173724173254
Jun '12154021175257



MRO SuppliesHand to Mouth30 Days60 Days90 Days6 Months1 Year+Average Days
Sep '1244361631027
Aug '1246381132027
Jul '1247361151026
Jun '1243401132131


Source - Institute for Supply Management

(www.steelguru.com)

Get best prices for Galvanized Beams
Steel Pipes Fittings
Steel ball supplier
We also deal in aluminum products like Aluminum Extrusion Profiles

This is alternative content.

/
More International News