Contractor successful in retaining a judgment against Nakheel
249 times viewed.
Friday, 10 Feb 2012
EmailButton
Pdf_button

A contractor has been successful in a judgment against Nakheel PJSC. Technical Architects General Contracting Company LLC held onto a judgment against Nakheel for over AED 58 million in the Dubai World Tribunal.

Nakheel has been ordered to pay contracting company TAGC AED 58 million at a hearing held on February 7th 2012 before the eminent panel of DWT members, Sir Anthony Evans, Sir John Chadwick and His Honour Judge Michael Hwang for work completed in an unfinished contract to construct 31 multi storey residential buildings at Mogul 3 in Discovery Gardens.

TAGC was contracted by Nakheel to construct the buildings in December 2007 for a value of over AED 950 million. By November 2008, Nakheel instructed TAGC to suspend work due to Nakheel's growing parlous financial state. The contract was subsequently terminated on January 19th 2009. Under the terms of the contract, an assessment had to be made for the value of the work done by TAGC up to the date of termination and the various additional amounts that TAGC was entitled to claim for in light of the termination. TAGC submitted a claim for payment to Nakheel for the amount of AED 311 million in March 2009.

Following negotiations between TAGC and Nakheel, a full and final settlement was agreed to in June 2009 whereby payment was to be made by Nakheel to TAGC of AED 58 million. However, Nakheel was not able to pay the amount in one go and it was agreed the payment would be made over an 11 month period ending April 2010 but Nakheel failed to pay any of the AED 58 million.

In January 2011, TAGC served proceedings on Nakheel in the DWT claiming just over AED 73 million which comprised the agreed settlement amount of AED 58 million plus interest charges and loss of profit.

On June 8th 2011, TAGC entered a judgment against Nakheel for the total amount based on a default of Nakheel in acknowledging service of the proceedings because it appears Nakheel overlooked the fact that the DWT papers had been delivered to its head office had not been attended to.

Mr Partner Anthony Edwards head of Hadef & Partners' Engineering & Construction practice in Dubai said that "This is a significant victory for our client TAGC in its efforts to recover its costs incurred under the terms of the contract it entered into with Nakheel. The DWT affirmed it had jurisdiction to hear this case and there was clear evidence the settlement agreement had been entered into and that Nakheel had failed to prove the amount had not been agreed."

Mr Edwards said that "Compromises which require a contractor to substantially reduce its initial claims to its employer are not uncommon in this market. Where a contractor is compelled to settle for less, obviously not to its liking, it may take comfort that it may not therefore be forced into lengthy arbitration proceedings under the dispute resolution provisions in the original contract. The contractor should seek to rely on its separate settlement agreement."

Expanded Metal by Anping County Huijin Wire Mesh Co., Ltd.
Galvanized Steel by Beijing Xinruilufeng Industry and Trade Co., Ltd.
Wire Mesh Manufacturers & Suppliers
Aluminium Sheets Manufacturers & Suppliers

jspl
Stemcor
Middle East News
 
Disclaimer|Copyright Policy|Privacy Policy|About us|Feedback|Contact us|FAQ|Site Map|Know about SteelGuru