Surya Alloy to receive environmental clearance by October
ProjectsToday reported that Surya Alloy Industries is expected to receive environmental clearance for the phase 3 of its integrated steel mill project in Bardhaman district of West Bengal by October 2007.
Surya Alloy Industries is setting up an integrated steel plant in 4 phases with an investment of INR 400 crore.
Phase 1 includes ERC unit
Phase 2 includes arc furnace, vacuum de casting unit
Phase 3 includes mini blast furnace, sinter plant
Phase 4 includes structural rolling mill.
The first 2 phases of the project has been completed. Work on phase 3 is scheduled to commence by November 2007 and get completed within 18 months. Surya Alloys officials informed that the structural rolling mill is underway and completion expected by June 2008.