Sglogo_1

 

Events Reports Directory Forum Articles Jobs in Steel Resume Post Links Currency Archive Metal Rate Archive Glossary Import Duty Structure Incoterms 2000 Technical Info Trade Leads Currency Codes Contact Us Disclaimer Feedback Privacy Policy Site Map

 

FAIL (the browser should render some flash content, not this).

October 14, 2008


TATA Steel Thailand furnace project facing construction delays

Reuters reported that Thai steel major TATA Steel (Thailand)’s mini blast furnace project would be delayed and cost slightly more than expected due to construction delays.

The furnace project, operated by its 99.66% owned subsidiary NTS Steel Group, is expected to be completed in second quarter of 2009 instead of the third quarter of 2008.

TATA Steel (Thailand) has also raised the project budget to THB 3.8 billion (USD 120 million) from an earlier THB 3.4 billion.