Tenova receives FAC for walking beam furnace at the Arcelor Mittal Poland

Tenova LOI Italimpianti Genoa has successfully received the FAC Certificate for the Arcelor Mittal 450 tonne per hour walking beam furnace of the new MSPKK Hot Strip Mill located at Krakow in Poland in the very short period of only four months from the start up.

The scope of Tenova contract, included in Siemens VAI package, was engineering, supply and supervision services for erection & commissioning.