Pratibha Industries has bagged an order worth INR 294.30 crore from the Uttar Pradesh Jal Nigam for the Meerut water supply project.
The scope of the order envisages execution of 100 mld water treatment plant with PLC / SCADA, laying of 1,500 mm to 500 mm dia PSC pipe feeder main, RCC overhead tank, laying & commissioning of distribution system & rising mains, tube wells, pump houses etc including operation and maintenance for five years.
The project is to be executed in 24 months including four months trial run.