In the metallurgical plant them AK Serov completed overhaul shears August 1st after the commissioning, the equipment was put into operation.
In the five years shears French company is the first renovation of this magnitude. At the aggregate installed a new cylinder cut, repaired Knife frame, which are movable knives. In addition, the press-shears have replaced the main protective elements cameras pressing, repaired the main conveyor, the mechanisms of loading and unloading have audited the hydraulic system.
Mr Andrew Lorenz chief engineer of the plant said "Experts project management found the technical solutions and prepare the necessary documentation that allowed them to purchase spare parts for repair from domestic manufacturers directly from the put only cylinder it has reduced the cost of repair."