Equinor’s Martin Linge Oil & Gas Filed on Stream
Martin LingeEquinor

Equinor’s Martin Linge Oil & Gas Filed on Stream

Equinor announced that on 30 June, the Martin Linge oil and gas field in the North Sea came on stream. The field is powered from shore, resulting in low

Equinor announced that on 30 June, the Martin Linge oil and gas field in the North Sea came on stream. The field is powered from shore, resulting in low CO2 emissions, and operated from its onshore control room. Expected recoverable resources are approximately 260 million barrels of oil equivalent. At plateau the field will produce around 115 000 boe per day.

The Martin Linge platform receives power via the world’s longest alternating-current sea cable measuring 163 kilometres from the onshore substation at Kollsnes in Western Norway. The platform was connected to shore power in December 2018 and was soon followed by the storage vessel on the Martin Linge field. This is the world’s first storage vessel receiving power from shore.

Martin Linge is also the first platform on the Norwegian continental shelf to be put on stream from shore. The production wells and processing plant are operated from the control room in Stavanger, and the offshore operators use tablets in the field to interact with their colleagues in the onshore control room and operations centre. Onshore control room will reduce costs in the operating phase.

The Martin Linge project has faced many challenges. Production was originally scheduled to start in 2016. The costs of the Martin Linge field development have risen to BNOK 63 (2021 NOK), compared to the original 31,5 in the 2012 plan for development and operation (PDO).

Equinor acquired Total’s interests in the field in March 2018. At the same time, it took over the operatorship and responsibility for completing the field development project.