Turkish steel maker Kardemir Karabuk Demir Celik Sanayi ve Ticaret announced that the relining works for its blast furnace No 1, which were started at the end of 2021, have been completed and that the blast furnace has been recommissioned before the planned date. The investment cost of the 117-day works was approximately USD 18 million.The capacity of the blast furnace is expected to increase by 25% with the latest relining works & Kardemir aims to achieve annual steel production of 3.5 million tonnes
Turkish steel maker Kardemir Karabuk Demir Celik Sanayi ve Ticaret announced that the relining works for its blast furnace No 1, which were started at the end of 2021, have been completed and that the blast furnace has been recommissioned before the planned date. The investment cost of the 117-day works was approximately USD 18 million.The capacity of the blast furnace is expected to increase by 25% with the latest relining works & Kardemir aims to achieve annual steel production of 3.5 million tonnes