US Steel will restart the last idled 1.5 million short tons per year blast furnace 4 at its Gary Works steel mill in Indiana on 8 December amid higher demand

US Steel will restart the last idled 1.5 million short tons per year blast furnace 4 at its Gary Works steel mill in Indiana on 8 December amid higher demand and increasingly tight supply in the flat-rolled market. T

US Steel took the blast furnaces offline in March-April for a planned maintenance project but left it idle as the coronavirus pandemic roiled the domestic steel industry. In addition to idling the No 4 blast furnace, US Steel had also idled the 1.36 million short tons per year Gary Works No 6 blast furnace and the 1.2 million short tons per year No 8 blast furnace. Both the No 6 and No 8 blast furnaces have since restarted